COMMITTEE ON LEGISLATIVE RESEARCH

OVERSIGHT DIVISION



FISCAL NOTE



L.R. No.: 0844-01

Bill No.: SB 220

Subject: Business and Commerce: Electronic Transactions

Type: Original

Date: February 5, 2001




FISCAL SUMMARY



ESTIMATED NET EFFECT ON STATE FUNDS
FUND AFFECTED FY 2002 FY 2003 FY 2004
General Revenue ($205,087) ($41,017) $0
Highway ($49,639) ($56,128) ($57,534)
Total Estimated

Net Effect on All

State Funds

($254,726) ($97,145) ($57,534)



ESTIMATED NET EFFECT ON FEDERAL FUNDS
FUND AFFECTED FY 2002 FY 2003 FY 2004
Total Estimated

Net Effect on All

Federal Funds

$0 $0 $0



ESTIMATED NET EFFECT ON LOCAL FUNDS
FUND AFFECTED FY 2002 FY 2003 FY 2004
Local Government $0 $0 $0

Numbers within parentheses: ( ) indicate costs or losses.

This fiscal note contains 4 pages



FISCAL ANALYSIS



ASSUMPTION



Officials of the Department of Insurance, the Department of Revenue, and the Department of Conservation stated that they did not expect any direct fiscal or administrative impact due to the proposal.



Officials from the Secretary of State's Office (SOS) assume the rules, regulations and forms issued by the Office of Information Technology could require as many as 16 pages in the Code of State Regulations. For any given rule, roughly half again as many pages are published in the Missouri Register as in the Code because cost statements, fiscal notes and the like are not repeated in the Code. These costs are estimated. The estimated cost of a page in the Missouri Register is $23. The estimated cost of a page in the Code of State Regulations is $27. The actual costs could be more or less the SOS's estimated cost of $984 for FY 2002. The impact of this legislation in future years is unknown and depends upon the frequency and length of rules, filed, amended, rescinded or withdrawn.



Oversight assumes the SOS could absorb the costs of printing and distributing regulations related to this proposal. If multiple bills pass which require the printing and distribution of regulations at substantial costs, the SOS could request funding through the appropriation process. Any decisions to raise fees to defray costs would likely be made in subsequent fiscal years.



Officials of the Department of Transportation would request an Information Specialist, who would be responsible for coordinating applications and paperwork with the Office of Information Technology. (The Department of Transportation has its own computers separate from State Data Center.)



Officials of the Office of Administration's Office of Information Technology (OIT) would implement the proposal using contracted consultants. OIT would oversee statewide use of electronic transactions. This would comprise determining technical implications, developing security policies, reviewing and recommending standards, and promoting security and interoperability. OIT would use consultants from existing state contracts to produce recommendations for implementation and technical standards. OIT officials also noted that they would require significant ongoing efforts maintain standards and ensure legal compliance. The state government would need a variety of standards to ensure appropriate levels of use and compliance for different applications. OIT would also continually review national standards to ensure and extend electronic processes. They also note that the state is currently involved in a project to promote electronic commerce.



OIT officials would request additional resources for ongoing implementation of this proposal ASSUMPTION (continued)



through decision items in budget requests, as needed. Consulting expenses were projected using existing contracts rates for security consulting services, including project management and travel expenses. OIT officials estimate the initial implementation would take twelve months.



FISCAL IMPACT - State Government FY 2002

(10 Mo.)

FY 2003 FY 2004
GENERAL REVENUE FUND
Cost - Office of Information Technology
Equipment and Expense - Consulting ($205,087) ($41,017) $0
ESTIMATED NET EFFECT ON GENERAL REVENUE FUND ($205,087) ($41,017) $0
HIGHWAY FUND
Cost - Department of Transportation
Personal Service (1 FTE) ($32,052) ($39,424) ($40,409)
Fringe Benefits ($12,952) ($15,931) ($16,329)
Expense and Equipment ($4,635) ($773) ($796)
Administrative Cost MoDOT ($49,639) ($56,128) ($57,534)
ESTIMATED NET EFFECT ON HIGHWAY FUND ($49,639) ($56,128) ($57,534)



FISCAL IMPACT - Local Government FY 2002

(10 Mo.)

FY 2003 FY 2004
$0 $0 $0



FISCAL IMPACT - Small Business



This proposal could affect small businesses which would use electronic documents.



DESCRIPTION



This proposal would repeal the Missouri Digital Signatures Act (sections 28.600 through 28.684, RSMo) and replace it with the Uniform Electronic Transactions Act which would provide standards to make electronic transactions as enforceable as paper transactions if the parties involved agree to transact electronically.



The Act would not apply to transactions governed by laws governing wills, codicils or testamentary trusts and transactions covered by the Uniform Commercial Code other than DESCRIPTION (continued)



sections 400.1-107, 400.1-206, 400.2-101 to 400.2-725, and 400.2A-101 to 400.2A-532.



This legislation is not federally mandated, would not duplicate any other program and would not require additional capital improvements or rental space. The proposal would not affect Total State Revenue.



SOURCES OF INFORMATION



Office of Administration - Office of Information Technology

Department of Transportation

Department of Insurance

Department of Conservation

Department of Revenue

Secretary of State











Jeanne Jarrett, CPA

Director

February 4, 2001