State Capitol Renovation Project Update

JEFFERSON CITY — Construction work continues on the State Capitol building as the Missouri General Assembly stands adjourned during the summer months.

Construction work continues on the Senate wing of the Missouri Capitol on June 28, 2018
A construction crew works atop scaffolding surrounding the Senate wing of the Capitol on June 28, 2018. Construction will continue counterclockwise around the building.

The $40 million project, which began in March, will modernize the stonework of the building’s façades, dome and drum before the governor’s inauguration in January 2021. The Capitol’s south lawn serves as a staging zone for the construction, with scaffolding covering the building at multiple locations.

During construction, eastbound traffic on Capitol Drive has been diverted onto West Main Street, while westbound traffic has condensed from two lanes to one.

As of June 28, work is well underway on the Senate wing of the Capitol’s exterior. From there, workers will move counterclockwise toward the east façade, gradually making their way around the building.

On the south portico, the area of the building beneath the central columns, workers are busy removing damaged stonework in preparation for the arrival of new replacement stone, selected by the Missouri State Capitol Commission to match the color and consistency of the original material. Construction crews have caulked and ground the portico’s joints to ready it for the fresh stonework.

The Liberty Bell pavilion, north of the Capitol, on June 28, 2018
The Liberty Bell pavilion lies empty on June 28, 2018. The bell has been moved while the area undergoes repairs.

On the east terrace, crews are working to waterproof the stone. The terrace’s treads and balustrades — that is, the step bases and stair railings, respectively — have been entirely removed. The pointing and pinning of the base-level stone is almost finished, and workers have poured new concrete around the first-floor entrance.

Construction on Monument Plaza, directly north of the Capitol, has also advanced. The Liberty Bell pavilion slab is undergoing repairs, and a new curb is being installed to better blend with the area’s aesthetic. To address flooding, a new drain box has been positioned near the Veterans Memorial.

Work on the Capitol and surrounding grounds will continue in the coming years. Updated construction pictures, photographed at regular intervals, are available on the Missouri Senate website, allowing interested citizens to keep track of the project’s progress.